Home > Case Studies > A University Renovation : A Case Study

A University Renovation : A Case Study

By: Susan Hunt MA - Updated: 11 Jan 2013 | comments*Discuss
 
Rebuild Refurbish Building Sustainable

An award-winning project at the University of Surrey has led to an impressive “newish” campus without the impact of demolition and rebuild.

Surrey, like many universities in Britain, had a number of buildings from the late 1960s and 1970s, which were looking dated, had major fenestration failures and were becoming increasingly expensive to run.

But it carried out an analysis before deciding on a new building programme and discovered that refurbishment was the better option all round.

Cost Savings

The university’s Director of Estates and Facilities Management, Derry Caleb, said: “Our analysis showed that renovation would have a lower capital cost with much less impact than a new build but would still deliver similar energy efficiency and running costs.”

The university had undertaken other remodelling projects in the past and knew from this experience that a lot of the work could be done floor-by-floor while the buildings were still in use.

The decision was then taken to upgrade a number of buildings over a period of years – avoiding the environmental impact of a new build programme.

Good Structure

The 1960s buildings were all of similar construction - heavy concrete structures with concrete panels constructed off site, bison beam and screeded concrete floors and roof structure. They were a heavyweight design with large thermal inertia - deep plan design, vertical risers, single pipe heating systems and an overall well-thought through design.

  • As part of the project, around 14,000 m2 of double glazed, insulated panels were fitted in place of older single glazing across nine buildings and this massively reduced heating requirements.
  • Main ventilation plants were replaced, infrastructure plant was renewed and the district heating and cooling plants were expanded.
  • The university’s annual energy use has now dropped by around 8,000,000 KwH, heat loss is 60 per cent lower and its buildings-related C02 emissions have been reduced by more 2,000 tonnes per year.
“A rebuild project would have taken much longer and we would have needed to move staff to temporary accommodation in different locations,” said Derry.

“We were able to coordinate our remodelling with other University changes and managed to compress major projects into three or four month periods each year with minimal disruption.”

Worthwhile Results

He says the project proved that in many cases, older buildings are worth investment and if upgraded, can perform as well as most new buildings of similar design.

“I think our experience is very transferable to other large developments. We showed that renewal can be carried out sustainably and there are significant environmental benefits in more effective space management.”

Derry said the key lesson from Surrey’s refurbishment is that structural design needs to be proportioned correctly to allow for flexibility.

Buildings should be able to deliver a level of “churn” because departments change, teaching methods vary and academic disciplines alter.

“Floor to ceiling heights must be capable of allowing remodelling to take place and you need to consider how replacement of ventilation and infrastructure can be undertaken, either by floor or by building.

“The building design must have suitable sized vertical routes through a building to a replace infrastructure and services.

“The additional 1-2% on capital cost to allow for these elements will have an insignificant impact on short term capital but will have a major impact on the long term sustainability of individual buildings,” he said.

“If these elements are allowed for at construction stage, you have a more sustainable design that has longevity and helps to future-proof the project.

Design is Vital

“If a building is intended for a 60 year life, then it must be designed to allow for this type of major refit and the consequences of that work should be understood at design stage. “Since most institutional buildings ARE designed for this timescale, all we have done is carried out the refurbishment and remodelling that you should expect and plan for.

“We all recognise that these may not be architectural “gems” but they are sustainable and the feedback we’ve had from staff and students has been excellent.

“From their perspective, the internal environment is similar to that of a new building.”

You might also like...
Share Your Story, Join the Discussion or Seek Advice..
Why not be the first to leave a comment for discussion, ask for advice or share your story...

If you'd like to ask a question one of our experts (workload permitting) or a helpful reader hopefully can help you... We also love comments and interesting stories

Title:
(never shown)
Firstname:
(never shown)
Surname:
(never shown)
Email:
(never shown)
Nickname:
(shown)
Comment:
Validate:
Enter word:
SEARCH OUR SUSTAINABLE BUILD DIRECTORY...
IN TOWN / POSTCODE:
Topics
Latest Comments
  • Caroline
    Re: Transport Links to New Build Developments
    Hello, I own some small plots of land in Houndeslow that is green fields land. It is directly next to a main road…
    19 April 2019
  • Millie
    Re: Brownfield Sites
    Can someone erect an agricultural barn 10 year previously in open countryside and then claim it is 'a brown site' and can then use this as an…
    14 April 2019
  • Bev
    Re: Brownfield Sites
    Hi. I have 1.25 acres of land locked old water board reclaimed filter bed land. Works removed in1960 I own the surrounding land so not land…
    23 March 2019
  • M lally
    Re: Self Sufficient Housing Developments: A Case Study
    What do I need to do to get involved with something like this. Thanks Martin
    22 March 2019
  • Pinky
    Re: Stone Construction
    Is the wastage of remaining stone is used for recycling if used where it is useful nd what is the process
    19 March 2019
  • Just William
    Re: Brownfield Sites
    I have 6 hecs land use for Haulage residential and eqestrian and sales and doing b &b machine sales repairs sale of 4 x 4 etc used by us since…
    14 March 2019
  • https://contractorsi
    Re: Underground Construction
    This was a excellent informative post you have shared on this page about the resident form in uk but In the summer, that 55-degree soil…
    7 March 2019
  • saman
    Re: Insulation Materials
    it is really interesting however you can improve this site by adding more images related to this project.
    4 March 2019
  • Oneshitatatime
    Re: Composting Toilet: Clean Enough for Environment Agency?
    Hello, My wife and I have been using a compost toilet for the last 2 years. It is simple,…
    17 February 2019
  • mark
    Re: Reclaimed Materials
    To whom this may concen I am makeing a few enquiries to see if you would be interested in some meterials i have available left over from a…
    12 February 2019